Initiation Stage

...

No

What to do?

Example/Experience

Remarks

1

Project objective is identified

  • Usually is stated by client during demo whether they need or not the bank recon automation

  • This applet should speed up the bank recon (mgt report) process monthly

BI  Features - BI - Feature List  

2

An appropriate response to the objective is documented  in a business case with recommended solution options

  • All requirements from the demo / meet up with clients is written in Minute of Meeting (MOM) 

  • MOM should be properly dated and summarised which will be referenced when doing Planning Stage

https://drive.google.com/drive/u/0/folders/1x6LbZ2AW8856jxEYa7-tbJLtJjaur6AY  

3

Investigate whether each option addresses the project objective 

  • N/A 


4

Final recommended solution is determined

  • It is BI


5

“Can we do the project?” is discussed

  • Yes because BI is a product now


6

“Should we do the project?” is discussed

  • Yes because Bank Recon Applet is a product now

  • Quotation is signed from customer (acknowledged)

How to create Issues: /wiki/spaces/WPMO/pages/2177827263  

7

Major deliverables and the participating work groups are identified

  • Communicate with tech lead (For BI, please liaise with MIS Head (Arri))

  • Find out the resources names in the org chart and see JIRA Master List for their current targets and fit where is ‘idle’

  • From quotation  -Identify these:

    • How many Author & Reader access

    • What type of report (which category)